SV Restless

 

Framing done, collision bulhead/anchor locker at waterline at bow in, nearly ready for plating. This is about 1 year into it, working 60-70 hours a week in the winter. Burned out; time to go swordfishing, but good progress. Basically it took 1 winter to frame, 1 winter to plate, 1 winter to weld, 1 winter to grind and fair, and then quite a few winters of detail before the metal work was done. Next